Schedule by Specific Dates

A task can run on specific dates rather than follow a recurring schedule, and specific dates can be added to a recurring schedule. The Specific Dates run day option allows you to schedule specific dates on which your task will run. You can schedule specific dates in any month of any year up to and including December 31, 2037.

  To schedule a task on specific dates

  1. In the Calendar Schedule tab, select Specific Dates.
  2. Click on the date in the calendar display or click New, enter a date, then click OK. The date appears in the calendar schedule list.
  3. To remove a date, select it in the calendar schedule list and click Delete.
  4. When you have finished selecting dates for your task, select another tab to make changes or click OK to close the dialog.